BidIntel — Preconstruction Leveling Matrix
Multimodal BOQ extraction, scope gap detection, and normalized bid leveling copilot for commercial general contractors.
PROJECT RMC-2608 • HEALTHCARE OUTPATIENT
Riverfront Medical Center
Package: 26 00 00 – Electrical Systems • Due Date: 18 Sep 2026 • BOQ Rev: 3.2
Lowest Quoted Bid
$795,000
Summit Power (Deceptive Low)
True Normalized Lowest
$840,000
Atlas Electrical (Full Scope)
Identified Cost Exposure
+$183,100
Unquoted GST + Scope Gaps
Copilot Scope Audit
2 Critical Gaps
Evidence linked from proposals
Bid-Leveling Matrix
Filter rows or click badges to compare scopes
| Scope Requirement | Atlas Electrical Quoted: $840,000 |
VoltWorks Cont. Quoted: $810,000 |
Summit Power Quoted: $795,000 |
|---|---|---|---|
| Temporary Power | ✓ INCLUDED | ✓ INCLUDED | ✓ INCLUDED |
| Testing & Commissioning | ✓ INCLUDED | ✓ INCLUDED | ✗ EXCLUDED (+$18k) |
| 18% GST Compliance | ✓ INCLUDED | ✓ INCLUDED | ✗ EXCLUDED (+$143.1k) |
| Fire Alarm Integration | ✓ INCLUDED | ? CLARIFY | ✓ INCLUDED |
| Warranty Period | 24 Months | 24 Months | 12 Mo (+22k) |
⟷ Scroll table horizontally for all details
⚡
Leveling Recommendation
Summit Power's initial quote appears $45,000 cheaper, but normalized scope analysis reveals unquoted GST and testing exclusions add +$183,100. Awarding to Atlas Electrical prevents mid-flight cost overruns.
Precon Copilot Feed
Automated proposal audit evidence
Copilot Audit Note: Ingested 3 PDF bids (148 total pages). Flagged 2 major scope exclusions in Summit Power's §3.4 and §5.1.
Action Recommended: Submit RFI #EL-04 to Summit Power regarding testing & commissioning fee exclusions before awarding package.